Capacity and delegation  ·  4 min read

Count the hours your team really has next month, after meetings, leave, and the work you already promised. Compare that with what the new project needs. If the new project does not fit, you have three choices: say no, push a date, or drop something. Guessing is not one of them.

Capacity check: real hours, hours already promised, and the new projectDesign team of four, next monthReal hours available380 h (4 × 95 h after meetings, admin, leave)Already promisedWebsite 180Brand 90Social 60Sales 4010 h freeNew campaign needs100 hIt does not fit. Three honest options: say not yet, move a date, or drop something. Here: push thebrand guidelines a month, which frees 90 h.
Fifteen minutes of arithmetic instead of a weekend of overtime.
1Capacity and delegation

"Sure, we can fit it in"

A client asks. Your boss asks. It is a good project. You say yes because saying no feels bad and because you have not done the math. Three weeks later, everyone is working late, something else slips, and the good project is not going well either.

Saying yes without counting is not generosity. It is a loan you take out in your team's name.

2Capacity and delegation

Step 1: Count real hours, not calendar hours

A full-time person has about 160 hours a month on paper. They do not have 160 hours of project time. Take off:

  • Meetings. For most people, 20 to 30%.
  • Email, messages, and admin. Another 10 to 15%.
  • Leave and holidays this month.
  • Helping others, interruptions, the unexpected. At least 10%.

For a typical person, 160 hours becomes about 90 to 100 hours of real project time. For a manager, less. Write down your number per person. If you are not sure, run a one-week time audit first.

3Capacity and delegation

Step 2: Subtract what is already promised

List every project and recurring job your team is already doing. Estimate the hours each needs this month. Add them up. Subtract from the real hours.

What is left is your true free capacity. For many teams, the answer is "almost nothing," and that is the first time anyone has seen it.

4Capacity and delegation

Step 3: Estimate the new project honestly

Use three numbers: best case, likely, worst case. Here is how. Use the likely number for planning. Keep the worst case in view.

5Capacity and delegation

Step 4: Compare

Free capacity: 60 hours this month across the team. New project likely needs: 120 hours. It does not fit. Not "it will be tight." It does not fit.

The capacity check tool does this arithmetic and shows the gap per person, so you can see who is overloaded, not just whether the team is.

6Capacity and delegation

Step 5: Choose, on purpose

If it fits, say yes with confidence. If it does not, you have exactly three honest options.

  1. Say no, or not yet. "We can start this on the 15th of next month."
  2. Move a date. "We can do it now if the website refresh slips two weeks."
  3. Drop or shrink something. "We can do it if we pause the newsletter this month."

Any of these is a real plan. "We'll make it work" is not.

7Capacity and delegation

A worked example

A design team of four. Each has about 95 real hours a month, so 380 total. Already promised: the website refresh (180), the brand guidelines (90), monthly social assets (60), and support for sales (40). That is 370. Free capacity: 10 hours.

A new client wants a campaign. Likely estimate: 100 hours.

The manager shows her director the numbers. They agree to push the brand guidelines by one month, which frees 90 hours. With the 10 spare, that covers the campaign. The decision took 15 minutes. Nobody worked a weekend.

How M-Tracker helps

Where M-Tracker fits

In M-Tracker, projects hold tasks with estimates, and the timer records actual hours, so what is "already promised" is a real number, not a feeling. The capacity view in projects shows planned hours against available hours per person and per week. When a new request comes in, you can see where it would land before you say yes.

Start free

Try M-Tracker free14-day trial. No credit card. No employee surveillance.

How a task moves through M-Tracker: brief, work, review, improve, then the manager1BriefResult, audience,must include, due.Files and linksattached.2WorkThe person does itand attaches whatthey made.3ReviewM-Tracker comparesthe work with thebrief. One plainparagraph.4ImproveThey fix what ismissing while it isfresh.5ManagerSees work thatalready passed itsown test.No screenshots. No scores. The person sees the review first.

Copyright © 2020 – 2026 M-Tracker. All Rights Reserved. Privacy Policy