Time and estimates  ·  3 min read

For any task, write three numbers: the best case, the most likely case, and the worst case. Use them to get one expected number and to see how risky the task is. It takes one extra minute and it stops the "you said two days" conversation.

A three-point estimate: best, likely, worst, and the expected value0d1d2d3d4d5d6dbestlikelyworstexpected 3.3 days = (2 + 4×3 + 6) ÷ 6“Likely three days. Could be two. Could be six if the screenshots are late.”The spread (four days) is the risk. The unknown is the screenshots, so ask for them today.
Three numbers say what you actually know. One number pretends.
1Time and estimates

One number is a trap

"How long?" "Two days." Now two days is a promise. If it takes three, you were wrong. If it takes one, you were padding. One number cannot be honest, because you do not actually know. You know a range.

Three numbers say what you really know.

2Time and estimates

The three numbers

  • Best case. If everything goes right. No interruptions, no surprises.
  • Likely case. A normal day. Some bumps.
  • Worst case. The thing you are quietly worried about happens.

For a report: best case 1 day, likely 2, worst 4 if the data needs cleaning.

3Time and estimates

The simple math

To get one expected number from three, use this: (best + 4 × likely + worst) ÷ 6.

For the report: (1 + 4 × 2 + 4) ÷ 6 = 13 ÷ 6 = about 2.2 days.

Why count "likely" four times? Because it is the most probable. The best and worst cases pull the number a little, but not much. This formula has been used in project planning for decades. The three-point estimate calculator does the math and shows the spread.

4Time and estimates

The spread tells you the risk

Look at the gap between best and worst.

  • Best 1, worst 1.5: you know this task well. Plan on it.
  • Best 1, worst 4: there is a real unknown. Find out what it is before you promise anything.

A wide spread is not a bad estimate. It is an honest one. It is also a signal: do a small piece first, or get the unknown answered, then re-estimate.

5Time and estimates

How to say it

To your manager: "Likely two days. Could be one if the data is clean. Could be four if it is not. I will know by tomorrow lunch."

To a client: "We are planning on two days. If the data needs cleaning, it could be up to four, and we would tell you by tomorrow."

Both are more trustworthy than "two days," and both set up a cheap check-in instead of an expensive surprise.

6Time and estimates

Example

Priya is asked how long the FAQ page will take.

DaysWhy
Best2Screenshots arrive, content is approved first time.
Likely3One round of edits.
Worst6Screenshots are late and content needs two rounds.

Expected: (2 + 12 + 6) ÷ 6 = 3.3 days. Spread: 4 days. The risk is the screenshots. Priya asks for them today instead of on day three. The worst case shrinks to 4.

7Time and estimates

Where M-Tracker fits

In M-Tracker, tasks carry an estimate and the timer records the actual time. You and your manager can see estimate against actual across tasks, people, and projects. The pattern is visible, so estimates improve, and so do the plans built on them.

Start free

How M-Tracker helps

Make it a habit

Add three boxes to your task template: best, likely, worst. It takes a minute. After a month, compare your likely numbers with what actually happened. Most people find they are low by a steady amount. Once you know yours, your estimates get better without any other change.

Try M-Tracker free14-day trial. No credit card. No employee surveillance.

How a task moves through M-Tracker: brief, work, review, improve, then the manager1BriefResult, audience,must include, due.Files and linksattached.2WorkThe person does itand attaches whatthey made.3ReviewM-Tracker comparesthe work with thebrief. One plainparagraph.4ImproveThey fix what ismissing while it isfresh.5ManagerSees work thatalready passed itsown test.No screenshots. No scores. The person sees the review first.

Copyright © 2020 – 2026 M-Tracker. All Rights Reserved. Privacy Policy